EXERCISES, LESSON 2
INSTRUCTIONS: Answer the following items by completing the statement or by writing
the answer in the space provided at the end of the item.
After you have completed all of these items, turn to "Solutions to Exercises" at the
end of the lesson and check your answers with the solutions.
1.
Before conducting the safety analyzer start up and self test, ensure that:
a. No equipment is plugged into the unit.
b. The UUT is plugged into the safety analyzer.
c.
Power for the safety analyzer is on.
d. The display reads 1000 20.
2.
Which of the following tests is performed only on the ECG?
a. Power supply system voltage.
b. External meter, ohms test.
c.
External meter, volts test.
d. External meter, a/mv test.
3.
To perform the patient lead leakage current to ground test, set the ECG selector
switch to:
a. ALL.
b. CASE LEAKAGE.
c.
L1-GND.
d. RA-LA, RA-RL, and LA-RL.
MD0356
2-10